Island Lake Rd & Dexter Main St Corridor Improvements (Webster & Scio Twps)
Project Update #3
Roundabout Taking Shape
July 6, 2026
The roundabout at the intersection of Island Lake Road and Dexter-Chelsea Rd is taking shape. New concrete curbs and driveway approaches are being poured this week. The intersection of Island Lake Rd and Dexter-Chelsea Rd remains closed. Please follow the posted detours.
Next steps:
• Final shaping and compaction of the limestone base, supporting the asphalt pavement and concrete islands, will begin the week of July 6th.
• Asphalt paving is expected to start in late July.
• Concrete islands will be prepared; pour dates to be determined.
If you have any questions concerning this project, please contact Kevin Dubnicki, Project Manager, at (734) 327-6693, or via email at dubnickik@wcroads.org.
Pictured is the new roundabout intersection facing south at Island Lake Rd and Dexter-Chelsea Rd in Scio Township.