Island Lake Rd & Dexter Main St Corridor Improvements Roundabout Taking Shape

Jonathan Rodgers | Published on 7/6/2026

Island Lake Rd & Dexter Main St Corridor Improvements (Webster & Scio Twps)

Project Update #3

Roundabout Taking Shape

July 6, 2026

The roundabout at the intersection of Island Lake Road and Dexter-Chelsea Rd is taking shape. New concrete curbs and driveway approaches are being poured this week. The intersection of Island Lake Rd and Dexter-Chelsea Rd remains closed. Please follow the posted detours.

Next steps: 

             Final shaping and compaction of the limestone base, supporting the asphalt pavement and concrete islands, will begin the week of July 6th.

             Asphalt paving is expected to start in late July.

             Concrete islands will be prepared; pour dates to be determined.

If you have any questions concerning this project, please contact Kevin Dubnicki, Project Manager, at (734) 327-6693, or via email at dubnickik@wcroads.org.

 

Pictured is the new roundabout intersection facing south at Island Lake Rd and Dexter-Chelsea Rd in Scio Township. 

Project Web Page